Valid ISTQB Certified Tester CTFL_Syll2018 Exam Dumps – [2018 Dumps]

By | September 25, 2018
Vendor iSQI
Exam Code CTFL_Syll2018
Full Exam Name ISTQB Certified Tester Foundation Level
Certification Name ISTQB Certified Tester
Technology

Once you are up to appear in the iSQI ISTQB Certified Tester Foundation Level CTFL_Syll2018 exam. You may come across a variety of websites and platforms that will be facilitating you in achieving your goal. But afterwards you will find it that only a few of them provide you best assistance to pass iSQI ISTQB Certified Tester Foundation Level CTFL_Syll2018 Exam. In order to pass iSQI CTFL_Syll2018 Exam, the most important element is to check the quality of that particular iSQI ISTQB Certified Tester Foundation Level CTFL_Syll2018 exam dumps which you are selecting for dragging off your desired ISTQB Certified Tester CTFL_Syll2018 certification exam.

♥ 2018 Valid CTFL_Syll2018 Exam Dumps ♥

CTFL_Syll2018 exam questions, CTFL_Syll2018 PDF dumps; CTFL_Syll2018 exam dumps::CTFL_Syll2018 Dumps (196 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate iSQI CTFL_Syll2018 Exam Dumps:

Version: 8.0
Question: 1

Which of the following errors CANNOT be found with structure-based testing techniques?

A. Memory is leaking
B. Features are only partially implemented
C. Data structures that are used before initialization
D. Division by zero

Answer: A

Question: 2

Which of the following is correct?

A. Intrusive test tools are tools that do not exhibit the probe-effect
B. Testing tools can be used by both developers and testers
C. Use of testing tools is effective only when done as part of a test automation system
D. Testing tools allow developers do testing Use of such tools changes the role of the test team

Answer: B

Question: 3

The following sentences refer to the Standard for Software Test Documentation’ specification (IEEE
829). Which sentence is correct?

A. The key to high quality test documentation regimes is strict adherence to this standard
B. Any deviation from this standard should be approved by management, marketing & development
C. This test plan outline is relevant for military projects For consumer market projects there is a
different specification with fewer items
D. Most test documentation regimes follow this spec to some degree, with changes done to fit a
specific situation or organization

Answer: A

Question: 4

A software company adopts the V-model as their development life cycle. Which of the following
contains roles of a tester in this company?

A. Decide what should be automated, to what degree, and how.
B. Review test plans and set up test environments.
C. Coordinate the test strategy with the project managers
D. Introduce suitable metrics to measure the testing progress

Answer: B

Question: 5

Which of the following is an appropriate reason for maintenance testing?

A. Bugs found in the field after upgrading the operation system
B. Bugs found during system testing
C. Bugs found during unit testing
D. Bugs found during integration testing

Answer: A

Question: 6

Once a bug is fixed, it should be retested. What is the term used to define this type of testing?

A. Reliability Testing
B. Confirmation Testing
C. Maintainability Testing
D. Regression Testing

Answer: B